Uungula Wind Farm construction progress
Overview
The Uungula Wind Farm project near Wellington has progressed from the transport of infrastructure components to the successful installation of its first turbine.
In early August 2026, the transport of the first turbine blade began from the Port of Newcastle, traveling via the Golden Highway. Authorities issued warnings regarding these “mega-sized loads,” advising motorists to exercise caution and remain behind escort vehicles.
By late August 2026, Squadron Energy reported that the first turbine was fully erected and in motion following the installation of three 80-metre blades. The company stated that construction is more than two-thirds complete and the project is transitioning into the tower installation phase. Once fully operational, the 414MW wind farm is expected to power more than 220,000 homes.
Entities
Port of Newcastle · Uungula Wind Farm · Squadron Energy · Uungula Wind Farm · Live Traffic NSW
Timeline
-
8 days ago
[BUSINESS] 2 sourcesUungula Wind Farm completes first turbine installationThe first turbine is operational at the Uungula Wind Farm. The 414MW project by Squadron Energy is over two-thirds complete and aims to power more than 220,000 homes.
-
about 1 month ago
[BUSINESS] 4 sourcesUungula Wind Farm turbine blade begins transport from NewcastleDrone footage captured the first wind turbine blade traveling from the Port of Newcastle to the Uungula Wind Farm near Wellington, prompting traffic warnings for mega-sized loads.