Blumenau infrastructure and flood prevention projects
Overview
The city of Blumenau is managing various infrastructure developments. One project involves the construction of a new roundabout and water network in the Escola Agrícola neighborhood. This R$ 1,179,900.00 initiative, funded by a parliamentary amendment, aims to reduce traffic congestion and improve water supply for approximately 58,000 residents through the installation of a new water main.
Separately, larger-scale flood prevention works, including river desilting and the construction of an overflow channel, have faced a one-year delay. Despite a planned R$ 12 million investment in partnership with the state government, the municipality has not yet commenced work. Officials attribute the delay to necessary technical studies and project revisions required by the State Court of Accounts (TCE-SC) to ensure effectiveness. The project must still undergo bidding processes and environmental licensing before execution.
Entities
Samae · Blumenau · State Court of Accounts of Santa Catarina
Timeline
-
[POLITICS] 7 sourcesBlumenau flood prevention works delayed by one year
Flood prevention works in Blumenau, involving R$ 12 million in investments, remain stalled due to requirements for technical studies and environmental licensing.
-
[BUSINESS] 2 sourcesBlumenau to construct new roundabout and water network
Blumenau is investing R$ 1.1 million in a new roundabout at the Benjamin Constant intersection to improve traffic flow and safety, alongside planned water network upgrades.