Overview
In July 2026 the Philippines’ Department of Public Works and Highways (DPWH) began emergency operations after a massive landslide collapsed a 100‑meter stretch of the Davao‑Bukidnon highway. DPWH Secretary Vince Dizon ordered a temporary bypass on the remaining roadway segment, aiming to restore light‑vehicle traffic within weeks, while coordinating relief and relocation assistance for affected families and consulting Japanese engineers for long‑term slope stabilization.
A week later, heavy rains associated with Tropical Cyclone Kiyapo triggered severe flooding in Davao City. President Ferdinand Marcos Jr. announced that Dizon would inspect the flood‑hit areas and resume stalled flood‑control projects, notably completing the elevation of the Talomo River dike. Dizon blamed inadequate maintenance and unfinished works for the disaster, calling for a review of DPWH records and emphasizing the need to implement existing JICA‑supported flood‑control master plans.
By the end of July, DPWH accelerated work on two fronts. The ₱83.059‑million Dacudao Storm Drainage Project—featuring reinforced‑concrete box culverts and canal cleaning—was slated for completion by August to reduce flooding along Dacudao Road, though additional funding remains required under the JICA Flood Control Master Plan. Simultaneously, all lanes of the Marahan section of the Davao‑Bukidnon Highway stayed closed as DPWH conducted round‑the‑clock repairs, installing 44 steel sheet piles for emergency stabilization while motorists used designated detour routes. These actions illustrate DPWH’s shift from rapid, ad‑hoc repairs toward sustained infrastructure upgrades and mitigation in the Davao region, with Dizon steering both immediate response and longer‑term resilience efforts.
Timeline
-
2 days ago
[POLITICS] 3 sourcesDPWH Fast-Tracks Davao Flood Drainage and Highway Repair ProjectsDPWH Secretary Vince Dizon oversees the near‑completion of the Dacudao drainage project and orders 24/7 repairs of the collapsed Marahan section of the Davao‑Bukidnon Highway, closing the road while stabilizing
-
5 days ago
[POLITICS] 2 sourcesPhilippines DPWH chief Vince Dizon to inspect flood‑hit Davao City projectsDPWH chief Vince Dizon will inspect flood‑hit Davao City, blaming unfinished projects for the damage and ordering a quick finish of the Talomo River dike; President Marcos Jr. pledged new housing units.
-
10 days ago
[BUSINESS] 3 sourcesDPWH launches emergency bypass on landslide‑hit Davao‑Bukidnon highwayDPWH is fast‑tracking a temporary bypass and permanent repairs on the landslide‑damaged Davao‑Bukidnon highway, aiming to restore light‑vehicle traffic within weeks with Japanese consultants helping long‑term s
Sources