Monitor this situation.
Unsubscribe anytime.
[SITUATION] · [ACTIVE] · [BUSINESS]
2 clusters · 4 sources · 24 days · First seen · Last updated
Pohang AI data center development
Overview
The development of a dedicated AI data center in Pohang, South Korea, has progressed from capacity commitments to active construction.
Initially, NHN Cloud announced a lease commitment to secure 20MW of power and space at the facility, which is being developed by AI Factory Pohang PFV in the Gwangmyeong General Industrial Complex. This expansion is intended to support growing demand for GPU-as-a-Service (GPUaaS) and cloud services. To facilitate this, parent company NHN provided a debt guarantee of 110.1 billion won for NHN Cloud.
Subsequently, Hyundai Engineering & Construction commenced construction on the 40MW facility. To meet an accelerated 16.5-month timeline, the project utilizes precast concrete methods, Pre-Construction Services (PCS), and Fast-Track methods. The center is designed as a high-performance GPU-based facility featuring a liquid cooling system—noted as a first in Korea—to manage high-heat AI servers. The developer, Neo AI Cloud, intends for the infrastructure to be expandable to support next-generation GPUs.
Entities
Pohang · AI Factory Pohang PFV · Neo AI Cloud · NHN Cloud · Hyundai Engineering & Construction
Timeline
-
1 day ago
[BUSINESS] 2 sourcesHyundai Engineering & Construction begins construction on Pohang AI data centerHyundai Engineering & Construction has begun building South Korea’s first dedicated AI data center in Pohang, using advanced precast concrete methods to complete the 40MW facility in 16.5 months.
-
25 days ago
[BUSINESS] 2 sourcesNHN Cloud secures 20MW AI data center capacity in PohangNHN Cloud will lease 20MW of capacity at a new AI data center in Pohang to support its expanding GPU-as-a-Service and cloud infrastructure goals by 2027.
Sources
biz.heraldcorp.com · seoul.co.kr · thelec.kr · tokenpost.kr