Overview

The Santa Catalina Photovoltaic Solar Park in Corrientes, Argentina, is entering its final construction stages. Developed by Coral Energía, a company under Grupo Corven, the 20 MW project covers 40 hectares and represents an investment of approximately US$ 13.3 million.

Construction is currently over 60% complete, employing a workforce that is 75% local residents. Energy generation is expected to begin in mid-October, with full commercial operation and grid connection scheduled for October 2026. This project is part of a broader expansion by Coral Energía that includes the Bella Vista Solar Park, which together aim to provide clean energy to more than 23,000 Argentine households.

Entities

Juan Pablo Valdés · Corrientes · San Rafael · Grupo Corven · Genneia SA

Timeline

  1. 13 days ago

    [BUSINESS] 4 sources
    Santa Catalina Solar Park nears completion in Corrientes

    The Santa Catalina Photovoltaic Solar Park in Corrientes, Argentina, is nearing completion with a 20 MW capacity and a US$ 13.3 million investment to boost renewable energy production.

  2. 22 days ago

    [BUSINESS] 2 sources
    Mendoza Sur Solar Park project enters public hearing phase

    Genneia SA is developing the Mendoza Sur Solar Park in Argentina, a 404 MW project that will be the largest photovoltaic facility in the country.