Suame Interchange construction in Ghana

Overview

Construction of Phase 2 of the Suame Interchange in Kumasi, Ghana, is progressing toward a projected opening in October 2026. The project, managed by Rango Construction Company Limited, is approximately 87 per cent complete.

Key components include the construction of three overpasses at the Anomangye, Maakro, and Abusuakruwa junctions, as well as the expansion of the Offinso Road (N10) into a dual carriageway, which is currently 77 per cent complete. The project aims to reduce traffic congestion near the Suame Magazine vehicle repair hub.

Following the completion of Phase 2, contractors intend to shift focus to Phase 1, which is scheduled for completion in 2028 and includes a three-tier interchange and the widening of bypass roads. Previous delays to the project were attributed to national debt issues, pipeline relocation, and resident compensation.

Entities

Suame Interchange · Rango Construction Company Limited · Governs Kwame Agbodza · Ghana Highways Authority · Kwame Governs Agbodza

Timeline

  1. 4 days ago

    [BUSINESS] 2 sources
    Suame Interchange phase two expected to open by October 2026

    Phase two of the Suame Interchange in Kumasi, Ghana, is slated for completion by October 2026 to ease traffic congestion near the Suame Magazine industrial hub.

  2. 21 days ago

    [BUSINESS] 6 sources
    Suame Interchange Phase 2 expected to open by October 2026

    Phase 2 of the Suame Interchange in Kumasi is 87% complete and expected to open to traffic by the end of October 2026 to ease regional traffic congestion.