Togo gas pipeline maintenance and power disruptions
Overview
In early October 2026, Togo faced potential electricity disruptions due to scheduled maintenance on the West African Gas Pipeline. The West African Gas Pipeline Company (WAPCo) suspended natural gas deliveries to thermal power plants, prompting the state-owned utility Compagnie énergie électrique du Togo (CEET) to increase the use of expensive liquid fuels to maintain capacity. Despite these efforts, CEET warned that some areas might still experience power interruptions.
By late October, WAPCo reported significant progress on the Lomé pipeline maintenance. Following the successful replacement of a subsea valve and an inlet shut-off valve between October 14 and October 17, the project moved into its final phase. This stage involves draining and drying the pipeline for internal inspection using a magnetic flux leakage tool to ensure integrity. Gas transport is expected to resume by October 27, 2026.
Entities
Togo · Compagnie Énergie Électrique du Togo · West African Gas Pipeline Company · West African Gas Pipeline Company Limited · Nangbéto Dam
Timeline
-
[BUSINESS] 3 sourcesWAPCo announces gas transport resumption in Togo
WAPCo expects to resume gas transport through the Lomé pipeline by October 27 following successful valve replacements and ongoing integrity inspections.
-
[BUSINESS] 2 sourcesTogo faces power disruptions due to gas pipeline maintenance
Togo faces potential power outages from October 7 to 22, 2026, as gas pipeline maintenance disrupts fuel supplies to thermal plants. CEET will use costly liquid fuels to minimize disruptions.