Vietnam power grid infrastructure development

Overview

Vietnam continues to expand its power grid and transmission infrastructure to meet rising demand. In Central Vietnam, the Central Vietnam Power Corporation (EVNCPC) is investing approximately 4,324 billion VND into the Quảng Trị province grid for 2026–2030. This includes 12 categories of 110kV projects to add 102.5 km of transmission lines and nearly 400 MVA of transformer capacity, targeting a projected 13,000 MW increase in power capacity. EVNCPC officials have conducted field inspections in the Trieu Phong and Hai Lang districts to ensure the grid can support industrial projects like the Southeast Quang Tri Economic Zone and the Capella Quang Tri Industrial Park.

In Northern Vietnam, the National Power Transmission Corporation (EVNNPT) is accelerating four critical projects: 500 kV substations in Hai Phong, Thai Binh, and Bac Ninh, and a 220 kV substation in Yen Dung. While land clearance is progressing, projects face hurdles such as bidding delays for equipment and difficulties sourcing materials like leveling sand. The Northern Power Corporation (EVNNPC) reported an 11.49% increase in commercial electricity output for the first nine months of 2026, reaching 89.31 billion kWh. To manage this, the corporation energized 45 110kV grid projects and 801 medium and low-voltage projects, contributing to a 50.14% decrease in average power outage time.

In Southern Vietnam, the Southern Power Corporation (EVNSPC) commenced 46 110kV grid projects and energized 64 projects at the 220kV and 110kV levels during the first nine months of 2026, with a disbursement of 13,278.3 billion VND. EVNSPC is prioritizing industrial zones and aims to extend its N-1 reliability standard to residential and business customers by 2028.

Entities

Quang Tri · Vietnam Electricity · Capella Quang Tri Industrial Park · EVNGENCO3 · Southern Power Corporation

Timeline

  1. [BUSINESS] 2 sources
    EVN entities focus on power supply and production in Vietnam

    EVNCPC is inspecting power infrastructure in Quang Tri to support industrial growth, while EVNGENCO3 reports meeting 72% of its annual power production target for 2026.

  2. [BUSINESS] 2 sources
    EVNSPC accelerates power infrastructure investment in southern Vietnam

    EVNSPC is accelerating power grid investments in southern Vietnam to ensure energy security and support industrial growth and FDI inflows through enhanced infrastructure reliability.

  3. [BUSINESS] 6 sources
    Northern Power Corporation reports 11.49% increase in electricity output

    Northern Power Corporation (EVNNPC) saw an 11.49% increase in electricity output during the first nine months of 2026, driven by grid investments and improved operational efficiency in Vietnam.

  4. [BUSINESS] 3 sources
    EVNNPT accelerates four key power projects for Northern Vietnam

    EVNNPT is expediting four major 500 kV and 220 kV substation projects in Northern Vietnam to secure the regional power supply despite procurement and material supply challenges.

  5. [BUSINESS] 2 sources
    EVNCPC to invest 4,324 billion VND in Quảng Trị power grid

    EVNCPC plans to invest over 4,300 billion VND in Quảng Trị's power grid from 2026 to 2030 to support massive increases in regional power generation capacity.