PPC S.A. digital and service infrastructure expansion
Overview
PPC S.A. (DEI) is advancing strategic initiatives to expand its digital and service infrastructure in Greece, specifically targeting the transformation of the Kozani region in Western Macedonia. A central component is the development of a major data center hub at the former Agios Dimitrios power plant site, a project designed to transition the region from lignite-based energy production toward a technology and clean energy hub. Under a binding Memorandum of Understanding (MoU), AWS will lease the facility for 15 years once construction is complete. PPC will provide the land, buildings, and energy infrastructure, while AWS will install and operate the IT infrastructure. The total investment for this specific development is estimated at approximately €2.3 billion, with DEI contributing roughly €1.2 billion for infrastructure and AWS investing approximately €1.1 billion for IT equipment. The project’s initial phase features a power capacity of 300 MW, developed in four 75 MW modules, with potential expansion up to 1 GW. To support Amazon’s goal of net-zero carbon emissions by 2040, AWS will purchase energy from PPC through long-term Power Purchase Agreements (PPAs) using renewable sources. The first phase of the development is expected to be completed by the end of 2028. As of late September 2026, the transition is progressing following approval from the Ministry of Environment and Energy to dismantle cooling towers and other infrastructure at the Agios Dimitrios site. This hyperscale development is being framed as a critical step toward European digital sovereignty and independence, particularly as Europe currently holds less than 5% of global computing power compared to 75% in the United States. The investment aligns with Greek government efforts to position the country as a digital hub in Southeast Europe and the Eastern Mediterranean.
Entities
Western Macedonia · Public Power Corporation S.A. · Kozani · Amazon Web Services · PPC S.A.
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 17 SOURCES] DEI and Amazon Web Services (AWS) signed a binding Memorandum of Understanding (MoU).
- [● 17 SOURCES] The data center will be located in Agios Dimitrios, Western Macedonia.
- [● 17 SOURCES] The initial phase of the project has a power capacity of 300 MW.
- [● 17 SOURCES] DEI is responsible for providing the land, buildings, and supporting energy infrastructure.
- [● 17 SOURCES] AWS will be responsible for installing and operating the IT infrastructure.
- [● 17 SOURCES] AWS plans to lease the data center under a 15-year long-term contract.
- [● 16 SOURCES] AWS will purchase electricity from DEI through long-term Power Purchase Agreements (PPAs) sourced from renewable energy.
Timeline
-
[TECHNOLOGY] 4 sourcesAmazon Web Services and PPC to build hyperscale data center in Greece
Amazon Web Services and PPC are partnering to build a massive hyperscale data center complex in Western Macedonia, Greece, to bolster European digital sovereignty and computing capacity.
-
[BUSINESS] 2 sourcesDEI AE and Amazon to build mega data center in Western Macedonia
DEI AE and Amazon Web Services are partnering to build a 300 MW data center at the Agios Dimitrios Power Plant site in Western Macedonia, Greece, with potential expansion to 1 GW.
-
[TECHNOLOGY] 23 sourcesDEI and AWS to develop mega data center in Western Macedonia
DEI and Amazon Web Services signed a binding MoU to build a 300 MW data center in Western Macedonia, Greece, with potential expansion to 1 GW. The €2.3 billion project focuses on digital and green energy.
-
[BUSINESS] 3 sourcesPPC to invest €5.8 billion in Kozani data center and energy hub
PPC plans a €5.8 billion investment to transform Kozani, Greece, from a lignite-mining region into a major European technology hub featuring large-scale data centers.
-
[BUSINESS] 2 sourcesPPC advances Kozani mega data center project
PPC is developing a mega data center hub in Kozani, Greece. Goldman Sachs suggests the project could significantly boost the company's valuation as it negotiates with global hyperscalers.
-
[BUSINESS] 21 sourcesPPC S.A. expands next-generation store network in Greece
PPC S.A. has expanded its next-generation store network in Greece to over 100 locations, offering integrated energy, technology, and connectivity services through specialized service zones.
-
[BUSINESS] 3 sourcesPPC S.A. advances plans for mega data center in Western Macedonia
PPC S.A. is negotiating with an international hyperscaler to build a 300 MW data center in Western Macedonia by 2028, with potential expansions up to 1 GW.
Sources
biznis.kurir.rs · businessdaily.gr · capital.gr · cna.gr · cnn.gr · cretaone.gr · dnews.gr · e-ptolemeos.gr · economix.gr · energymag.gr · enimerosou.gr · filathlos.gr · finance.in.gr · fortunegreece.com · fouit.gr · iefimerida.gr · ieidiseis.gr · ienergeia.gr · insider.gr · kefaloniamagazine.gr · kozan.gr · larissanet.gr · lifo.gr · lykavitos.gr · makpress.mk · mononews.gr · motorone.gr · naftemporiki.gr · newmoney.gr · newsbeast.gr · newsit.gr · ot.gr · philenews.com · protagon.gr · radio-lehovo.gr · real.gr · Reporter.gr · republika.mk · sbctv.gr · sofokleousin.gr · tharos.gr · thefaq.gr · thrakikiagora.gr · tromaktiko.gr · veriotis.gr · worldenergynews.gr · xaidarisimera.gr · ypodomes.com
This summary has been updated 13 times: see revision history