Saigon River pedestrian bridge construction progress

Overview

The Saigon River pedestrian bridge project reached a major milestone with the successful joining of its 3,400-ton steel arch on October 21, 2026. Prior to this, the assembly underwent successful load testing at the Dai Dung Mechanical Construction Trading JSC factory in Vung Tau. This test, utilizing 30 multi-axle self-propelled modular transporters and hydraulic systems, confirmed that the bridge's deflection and stiffness met design specifications.

The structure, designed in the shape of a water coconut leaf, was transported 124 km by water from Vung Tau to Ho Chi Minh City. To achieve the connection, engineers maneuvered the massive structure into position using a precise coordination of tugboats, barges, and specialized hydraulic systems. By utilizing hydrological data and tidal patterns, the team identified an optimal window between 6:00 AM and 9:00 AM when water levels were most stable. The joining process required moving the barge ‘centimeters at a time’ to align the two ends of the span, which had a gap of only approximately 25 centimeters.

Funded by Nutifood and constructed by the Dai Dung Group, the 720-meter bridge represents an investment of approximately $38.65 million. To ensure stability against wind speeds of up to 45 m/s, designers conducted three wind tunnel tests to optimize the curvature of the 33.2-meter wide roof. To support the arch, engineers constructed large underwater foundations, including a primary pier base covering nearly 1,800 square meters. These submerged bases are designed to protect against potential collisions from large container ships navigating the river.

Entities

Ho Chi Minh City · Saigon River · NutiFood · Thủ Thiêm · Bach Dang Wharf

Claims

What the coverage asserts, and how many sources carry each claim.

Timeline

  1. [TECHNOLOGY] 4 sources
    Saigon River pedestrian bridge features unique palm leaf design

    The Saigon River pedestrian bridge, featuring a palm leaf-shaped steel arch, is nearing completion with advanced engineering to withstand high winds and river vessel collisions.

  2. [BUSINESS] 4 sources
    Ho Chi Minh City pedestrian bridge reaches major construction milestone

    The 720-meter pedestrian bridge over the Saigon River in Ho Chi Minh City has reached 90% completion after its main span was successfully joined.

  3. [BUSINESS] 13 sources
    Saigon River pedestrian bridge reaches major milestone with steel arch connection

    The Saigon River pedestrian bridge, featuring a 3,400-ton water coconut leaf-shaped steel arch, successfully completed its main structural connection on October 21 in Ho Chi Minh City.

  4. [BUSINESS] 10 sources
    Saigon River pedestrian bridge main span begins 124km transport journey

    A 3,400-ton steel main span for the Saigon River pedestrian bridge has begun a 124km transport journey to Ho Chi Minh City, with final assembly expected on October 21.

  5. [BUSINESS] 11 sources
    Saigon River pedestrian bridge completes 3,400-ton load test

    The Saigon River pedestrian bridge project has successfully completed load testing for its 3,400-ton steel arch structure in Vung Tau, moving closer to its scheduled joining in October 2026.

Sources

baochinhphu.vn · baogiaothong.vn · baoxaydung.vn · cafebiz.vn · cafef.vn · en.baoquocte.vn · es.vietnamplus.vn · fr.vietnamplus.vn · hoahoctro.tienphong.vn · htv.vn · kenh14.vn · kienthuc.net.vn · mekongasean.vn · nhandan.vn · soha.vn · thanhnien.vn · tienphong.vn · tuoitre.vn · vietnamplus.vn · vtv.vn