Sumatra disaster rehabilitation and reconstruction
Overview
Rehabilitation and reconstruction efforts following disasters in Sumatra are progressing, with a focus on stabilizing affected regions and accelerating housing construction. As of early October 2026, 39 out of 53 affected regencies and cities have returned to normal status, characterized by restored national access, operational basic services, and resumed market activities.
To expedite recovery, President Prabowo Subianto has ordered that the construction timeline for permanent housing (Huntap) be reduced from three years to two years. This directive aims to assist affected communities in rebuilding their lives more rapidly. Current data indicates that over 184,000 homes have been damaged. While temporary housing (Huntara) has reached 99.8 percent of its target with 20,770 units completed, permanent housing progress stands at approximately 3.26 percent, with 2,085 units completed out of a target of 57,027 and another 1,862 currently under construction.
In North Sumatra, the provincial government is accelerating a 2026 house renovation program. Through the Self-Help Housing Stimulant Assistance (BSPS) program, the province aims to realize 15,011 units, a significant increase from the 1,982 units provided in 2025. This includes 3,411 units in settlement areas, 4,505 in urban areas, and 7,065 in rural areas, with 9,068 units already in the processing stage. Additionally, the government is working toward completing 919 permanent housing units in North Sumatra by the end of 2026.
While most areas have stabilized, eleven regencies and cities still require special attention. Specifically, Central Tapanuli and North Tapanuli continue to manage infrastructure repairs and administrative tasks, such as the completion of village offices.
Entities
North Sumatra · Aceh · Ministry of Housing and Settlement Areas · West Sumatra · Muhammad Tito Karnavian
Timeline
-
[INTERNATIONAL] 4 sourcesSumatra disaster recovery: 39 affected regions return to normal
Recovery in Sumatra is progressing, with 39 of 53 affected areas returning to normal. President Prabowo Subianto has ordered the acceleration of permanent housing construction from three years to two.
-
[POLITICS] 3 sourcesNorth Sumatra accelerates 2026 house renovation program
North Sumatra is accelerating a massive housing program for 2026, targeting 15,011 house renovations and the completion of 919 permanent housing units by year-end.
-
[INTERNATIONAL] 2 sourcesSumatra floods cause widespread damage to infrastructure and schools
Recurring floods and landslides in Sumatra have damaged government infrastructure and 4,922 schools, prompting calls for better spatial governance and government-led school revitalization efforts.
-
[INTERNATIONAL] 3 sourcesSumatra disaster rehabilitation and reconstruction efforts accelerate
Rehabilitation and reconstruction efforts are accelerating in Medan and Aceh Tengah, focusing on physical repairs and accurate economic loss assessments to support regional recovery.
-
[INTERNATIONAL] 2 sourcesSumatra disaster recovery: Land provision urged for school relocation
Authorities are urging Sumatra's local governments to provide land for relocating 60 disaster-affected schools, while Aceh Utara receives over Rp328 billion in disaster relief aid.