Northern Territory gas‑driven hyperscale data centre plans

Overview

Energy North’s Project Ares and Beetaloo Energy’s Beetaloo Digital initiative have driven a rapid push to build gas‑powered hyperscale data centres in the Northern Territory. Energy North’s proposal for a 90‑hectare site at Murranji Station includes a 1,038 MW gas‑fired plant with solar support, a workforce village, and a 2 km airstrip. Beetaloo Energy has launched Beetaloo Digital, securing exclusive rights to a 185‑hectare parcel at Weddell for AI‑focused campuses that could consume up to 200 TJ of gas per day and generate up to 2 GW of on‑site power. In late July, Beetaloo Energy signed a non‑binding memorandum of understanding with Halliburton, valued at approximately US$26 billion (A$37 billion), to create a vertically integrated supply chain. To support midstream infrastructure, Beetaloo Energy and the Australian Gas Infrastructure Group (AGIG) have signed a non‑binding MOU to conduct preliminary assessments for a proposed 750-kilometre gas pipeline. This pipeline is intended to connect the Carpentaria Gas project to Darwin demand centres, including the Beetaloo Digital site, potentially utilizing the Northern Territory Government’s Territory Energy Link common-user infrastructure corridor. In August 2026, Formentera Partners and Daly Waters Energy announced the commencement of natural gas commissioning at the Sturt Plateau Compression Facility (SPCF) in the Beetaloo Basin. A 50/50 joint venture between Daly Waters Energy and Tamboran Resources Corporation, the SPCF has a nameplate capacity of 48.5 MMcf/d. Under a take-or-pay agreement lasting up to 15 years, 38.8 MMcf/d is contracted to the Northern Territory Government. The US$99 million project was completed on schedule, with five wells currently tied back to the plant. By September 2026, gas production officially commenced in the Beetaloo Basin, an onshore reserve estimated by the Northern Territory government to hold 430 trillion cubic feet of gas.

Entities

Beetaloo Basin · Northern Territory Government · Beetaloo Energy · Tamboran Resources · Tamboran Resources Corporation

Claims

What the coverage asserts, and how many sources carry each claim.

Timeline

  1. 21 days ago

    [BUSINESS] 4 sources
    Beetaloo Basin gas production begins in Northern Territory

    Gas production has begun in Australia's Beetaloo Basin, a project expected to generate A$17 billion but facing criticism from environmentalists and disputes over Aboriginal land rights.

  2. 28 days ago

    [BUSINESS] 5 sources
    Beetaloo Basin gas plant begins commissioning in Northern Territory

    Formentera Partners and Daly Waters Energy have begun commissioning the Sturt Plateau Compression Facility, enabling natural gas sales from the Beetaloo Basin to the Northern Territory.

  3. about 1 month ago

    [BUSINESS] 4 sources
    Beetaloo Energy and AGIG partner on 750km Northern Territory gas pipeline

    Beetaloo Energy Australia and AGIG have signed an MOU to plan a 750km gas pipeline in the Northern Territory to support a proposed gas-to-power AI data centre development.

  4. about 1 month ago

    [BUSINESS] 3 sources
    Beetaloo Basin gas production scheduled to begin next month

    Gas production is set to begin in Australia’s Beetaloo shale basin next month, aiming to boost LNG capacity despite environmental opposition regarding pipeline financing.

  5. 2 months ago

    [BUSINESS] 6 sources
    Beetaloo Energy partners with Halliburton on AI‑powered gas‑to‑data‑centre project in Australia

    Beetaloo Energy and Halliburton have signed an MOU to build an AI‑driven gas‑to‑data‑centre project at Weddell, NT, using Beetaloo Basin gas to supply dedicated power for data centres across the Asia‑Pacific.

  6. 2 months ago

    [TECHNOLOGY] 10 sources
    Beetaloo Energy rolls out gas‑powered AI data centre plan in NT

    Beetaloo Energy launched Beetaloo Digital, securing 185 ha at Weddell for a gas‑powered AI data centre delivering up to 2 GW, while a separate off‑grid project near the Beetaloo basin seeks AU$28 bn to build a

  7. 3 months ago

    [TECHNOLOGY] 3 sources
    Project Ares hyperscale data centre proposal unveiled for NT outback

    Project Ares proposes a 90‑ha off‑grid hyperscale data centre in the NT, powered by gas and solar; Greenpeace urges a moratorium over emissions and regulatory gaps.

Sources

abnnewswire.net · bdh.de · boereport.com · brisbanetimes.com.au · brunswick.unitingchurch.org.au · businessday.com.au · esdnews.com.au · europesays.com · eveningreport.nz · greenpeace.org.au · lngprime.com · m.smh.com.au · mondialnews.com · nabidka-pujcek.cz · norskeanlegg.no · oilprice.com · perthnow.com.au · reneweconomy.com.au · stockhead.com.au · stockjournal.com.au · stocktitan.net · theage.com.au · thenextweb.com · theqldr.com.au · thewest.com.au