Northern Territory gas‑driven hyperscale data centre plans
Overview
Energy North’s Project Ares and Beetaloo Energy’s Beetaloo Digital initiative have driven a rapid push to build gas‑powered hyperscale data centres in the Northern Territory. Energy North’s proposal for a 90‑hectare site at Murranji Station includes a 1,038 MW gas‑fired plant with solar support, a workforce village, and a 2 km airstrip. Beetaloo Energy has launched Beetaloo Digital, securing exclusive rights to a 185‑hectare parcel at Weddell for AI‑focused campuses that could consume up to 200 TJ of gas per day and generate up to 2 GW of on‑site power. In late July, Beetaloo Energy signed a non‑binding memorandum of understanding with Halliburton, valued at approximately US$26 billion (A$37 billion), to create a vertically integrated supply chain. To support midstream infrastructure, Beetaloo Energy and the Australian Gas Infrastructure Group (AGIG) have signed a non‑binding MOU to conduct preliminary assessments for a proposed 750-kilometre gas pipeline. This pipeline is intended to connect the Carpentaria Gas project to Darwin demand centres, including the Beetaloo Digital site, potentially utilizing the Northern Territory Government’s Territory Energy Link common-user infrastructure corridor. In August 2026, Formentera Partners and Daly Waters Energy announced the commencement of natural gas commissioning at the Sturt Plateau Compression Facility (SPCF) in the Beetaloo Basin. A 50/50 joint venture between Daly Waters Energy and Tamboran Resources Corporation, the SPCF has a nameplate capacity of 48.5 MMcf/d. Under a take-or-pay agreement lasting up to 15 years, 38.8 MMcf/d is contracted to the Northern Territory Government. The US$99 million project was completed on schedule, with five wells currently tied back to the plant. By September 2026, gas production officially commenced in the Beetaloo Basin, an onshore reserve estimated by the Northern Territory government to hold 430 trillion cubic feet of gas.
Entities
Beetaloo Basin · Northern Territory Government · Beetaloo Energy · Tamboran Resources · Tamboran Resources Corporation
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 6 SOURCES] Beetaloo Energy signed a memorandum of understanding with Halliburton to advance the Beetaloo Digital gas‑to‑data centre project.
- [● 6 SOURCES] The project will be located at a 185‑hectare site in Weddell, near Darwin, in the Northern Territory.
- [● 6 SOURCES] The Beetaloo Basin holds vast untapped gas resources that will underpin the project.
- [● 5 SOURCES] Halliburton will provide subsurface consulting, field‑development planning, drilling services and modular gas‑fired power solutions for hyperscale data centres and AI infrastructure.
- [● 5 SOURCES] The project aims to generate dedicated power for data centres, reducing reliance on the existing Northern Territory electricity grid.
- [● 5 SOURCES] The project is expected to provide baseload electricity for the region and support growth of data centres across the Asia‑Pacific.
- [● 4 SOURCES] The partnership is valued at about US$26 billion (A$37 billion).
- [● 4 SOURCES] The Northern Territory Government granted Beetaloo Energy exclusivity over the Weddell site.
Timeline
-
21 days ago
[BUSINESS] 4 sourcesBeetaloo Basin gas production begins in Northern TerritoryGas production has begun in Australia's Beetaloo Basin, a project expected to generate A$17 billion but facing criticism from environmentalists and disputes over Aboriginal land rights.
-
28 days ago
[BUSINESS] 5 sourcesBeetaloo Basin gas plant begins commissioning in Northern TerritoryFormentera Partners and Daly Waters Energy have begun commissioning the Sturt Plateau Compression Facility, enabling natural gas sales from the Beetaloo Basin to the Northern Territory.
-
about 1 month ago
[BUSINESS] 4 sourcesBeetaloo Energy and AGIG partner on 750km Northern Territory gas pipelineBeetaloo Energy Australia and AGIG have signed an MOU to plan a 750km gas pipeline in the Northern Territory to support a proposed gas-to-power AI data centre development.
-
about 1 month ago
[BUSINESS] 3 sourcesBeetaloo Basin gas production scheduled to begin next monthGas production is set to begin in Australia’s Beetaloo shale basin next month, aiming to boost LNG capacity despite environmental opposition regarding pipeline financing.
-
2 months ago
[BUSINESS] 6 sourcesBeetaloo Energy partners with Halliburton on AI‑powered gas‑to‑data‑centre project in AustraliaBeetaloo Energy and Halliburton have signed an MOU to build an AI‑driven gas‑to‑data‑centre project at Weddell, NT, using Beetaloo Basin gas to supply dedicated power for data centres across the Asia‑Pacific.
-
2 months ago
[TECHNOLOGY] 10 sourcesBeetaloo Energy rolls out gas‑powered AI data centre plan in NTBeetaloo Energy launched Beetaloo Digital, securing 185 ha at Weddell for a gas‑powered AI data centre delivering up to 2 GW, while a separate off‑grid project near the Beetaloo basin seeks AU$28 bn to build a
-
3 months ago
[TECHNOLOGY] 3 sourcesProject Ares hyperscale data centre proposal unveiled for NT outbackProject Ares proposes a 90‑ha off‑grid hyperscale data centre in the NT, powered by gas and solar; Greenpeace urges a moratorium over emissions and regulatory gaps.
Sources
abnnewswire.net · bdh.de · boereport.com · brisbanetimes.com.au · brunswick.unitingchurch.org.au · businessday.com.au · esdnews.com.au · europesays.com · eveningreport.nz · greenpeace.org.au · lngprime.com · m.smh.com.au · mondialnews.com · nabidka-pujcek.cz · norskeanlegg.no · oilprice.com · perthnow.com.au · reneweconomy.com.au · stockhead.com.au · stockjournal.com.au · stocktitan.net · theage.com.au · thenextweb.com · theqldr.com.au · thewest.com.au