Zlín Building 34 demolition halted after intruder
Overview
The July 9 fire that gutted the ninth-floor shoe-warehouse in Building 34 of Zlín’s former Baťa complex left the 11-storey tower half collapsed. After two weeks of firefighting, the blaze was declared extinguished on 22 July. Police are treating the incident as a possible crime of general danger caused by negligence.
The municipal building authority ordered the unsafe sections to be removed immediately and required full demolition by 15 December 2026. Owner Cream transferred the site to demolition contractor Build Synergy on 5 August. Using a Caterpillar 390 F UHD excavator (≈100 t) with a 42-metre arm and hydraulic shears, the crew began dismantling the main torso that week, working floor by floor. The schedule targets removal of the main structure within 25 working days, with debris cleared by the December deadline, provided static-condition and wind-speed limits are respected.
Demolition activities were recently interrupted following a security breach. An unidentified man entered the fire-damaged structure and reached as high as the fourth floor, prompting an immediate halt to work. Security cameras owned by Cream detected the intruder, and firefighters used a drone to locate him due to the risk of uncontrolled structural collapse in the eastern wing. The individual was found, exited the building, and was taken into police custody on suspicion of unlawful conduct.
The investigation into the fire’s cause continues, and demolition is expected to resume once safety concerns are addressed.
Entities
Cream · Zlín · Build Synergy · Marcel Schmidt · Baťovka industrial area
Timeline
-
6 days ago
[CRIME] 2 sourcesZlín building demolition halted after intruder enters unstable structureDemolition of a fire-damaged building in Zlín's Baťa complex was halted after a man trespassed into the unstable structure, reaching the fourth floor before being detained by police.
-
10 days ago
[BUSINESS] 5 sourcesDemolition of burnt Zlín high‑rise building beginsDemolition of the fire‑damaged 11‑storey Zlín building has begun, using a 100‑ton excavator and hydraulic shears, with the site to be cleared by Dec 15 and police probing the blaze as a possible crime.
-
13 days ago
[BUSINESS] 3 sourcesDemolition of fire‑damaged Building 34 in Zlín’s Baťovka area to beginBuilding 34 in Zlín’s Baťovka area, gutted by a July fire, will be handed to Build Synergy for demolition on 5 August, with work to finish the main torso within 25 days; police probe the blaze for negligence.
-
24 days ago
[CRIME] 5 sourcesZlín's fire‑damaged Cream tower ordered demolished by Dec 15A July fire in Zlín’s Cream‑owned tower caused partial collapse; police probe possible negligence. Authorities ordered full demolition by 15 December, with hazardous parts cleared within six weeks.
-
27 days ago
[BUSINESS] 4 sourcesZlín fire prompts demolition order for damaged Bata complex buildingA July 9 fire in Zlín’s former Bata complex damaged building 34, prompting a demolition order, extensive commercial losses and a criminal negligence investigation.
-
30 days ago
[CRIME] 3 sourcesZlín high‑rise building fire continues as temperatures dropA fire that broke out on 9 July in an 11‑storey Zlín building has been largely contained, temperatures are dropping, no injuries were reported, and police are investigating possible criminal negligence.
-
about 1 month ago
[BUSINESS] 6 sourcesZlín’s Historic Building 34 Set for Demolition After Devastating FireA massive fire in Zlín’s historic Building 34 caused extensive damage and partial collapse; demolition is planned after legal clearance, with major commercial losses reported.
-
about 1 month ago
[CRIME] 2 sourcesZlín high-rise fire collapses 34‑storey building, tourist sites remain openA July 9 fire in Zlín collapsed part of a 34‑storey building but caused no injuries; police probe possible negligence while tourist sites stay open.
-
about 1 month ago
[CRIME] 3 sourcesZlín high‑rise fire continues as firefighters cool collapsed buildingA blaze in Zlín’s former Bata factory complex has left an 11‑storey building partially collapsed; firefighters continue cooling the wreckage while police probe possible negligence.
-
about 1 month ago
[BUSINESS] 33 sourcesFire devastates historic Bata factory in Zlín, Czech RepublicA fire at the historic Bata factory in Zlín, Czech Republic caused building collapse, destroyed up to 75,000 pairs of shoes and caused damage estimated over €150 million; police are investigating possible negl
Sources
5plus2.cz · Aktualne.cz · aldia.cat · asb-portal.cz · bedaromano.blog.ilsole24ore.com · blesk.cz · ceskenoviny.cz · cesky.radio.cz · ct24.ceskatelevize.cz · CT24.cz · ct24.cz · denikn.cz · e15.cz · edgesports.com · eet.denik.cz · games.tiscali.cz · gazeta.pl · haschcon.com · hausergroup.com · hnonline.sk · information.com · jcted.cz · koffiefabriek.nl · krajskelisty.cz · m.novinky.cz · maps.in.gr · medium.seznam.cz · medonet.pl · metro.cz · nasregion.cz · nextvbrasil.com · physicalers.com · policja.pl · pozary.cz · protothema.gr · reader.gr · seznamzpravy.cz · sofokleousin.gr · strategie.e15.cz · studiotamani.org · topky.sk · tyden.cz · uni.wroc.pl · vitjedlicka.blog.idnes.cz · wiadomosci.onet.pl · www2.iefimerida.gr · zlinsky.denik.cz
This summary has been updated 2 times: see revision history